$6.7m boost to rebuild and protect Fraser Coast coastline

Published on 18 February 2026

Sand bag barrier around the base of a shoreline fig tree at Maaroom beach, temporarily preventing further beach eroision

Fraser Coast Regional Council has secured $6.737 million in funding to repair cyclone‑damaged foreshore areas ensuring communities are better protected from future severe weather.

The funding is part of the $74 million Environmental Recovery Package, jointly supported by the Australian and Queensland Governments.

Fraser Coast Mayor George Seymour said eight Queensland councils are to receive funding, with the Fraser Coast successful in securing support for four coastline projects.

“Cyclone Alfred caused significant damage across the Fraser Coast last March, eroding dunes, weakening natural buffers, and leaving debris throughout key waterways,” he said.

“Council sought this funding because the impacts were far more than cosmetic - they affected public safety, environmental health, and the natural systems that shield our communities during major storms.

“The funding will support four priority projects, each addressing vulnerabilities exposed by Cyclone Alfred”.

  • Moolyyir Creek Mouth – Hervey Bay ($200,000): Debris will be cleared and the creek banks stabilised through beach nourishment and revegetation to restore natural water flow.
  • Maaroom – Sand Pushing & Temporary Protection ($75,000): The eroded dune face will be rebuilt and planted with vegetation to restore a natural barrier and minimise further erosion.
  • Poona Foreshore – Breakwater & Dune Management ($180,000): A breakwater consisting of large sand containers will be constructed and dune vegetation restored to protect the shoreline.
  • Pialba, Scarness, Torquay & Urangan – Major Beach Nourishment ($6.282 million): Sand lost during the cyclone will be replaced and dune systems stabilised in sections to strengthen natural storm buffering.

Cr Seymour said this program is focused on resilience, not just repair.

“The goal is to ensure that when the next major weather event hits, our coastline is stronger, safer, and better equipped to protect homes, infrastructure, and natural assets,” he said.

“All works are scheduled for completion by 30 June 2027, with each project subject to further approvals and consultation with the State Government.

“Council is committed to ensuring this investment delivers long‑term benefits for the Fraser Coast, protecting our environment, supporting safer communities, and strengthening the natural systems that make our region unique.”