Hervey Bay Community Hub costs

Published on 19 November 2026

FCRC_logo.png

Council approved an overall project budget of $126.5 million for the Hervey Bay Community Hub at its meeting on 26 July 2023.

This included the $108.7 million design and construction contract awarded to Hansen Yuncken, along with the Early Contractor Involvement fee, program and project management fees and project contingency costs.

Council has consistently made clear in its communications that the $108.7 million figure was the design and construction contract cost.

Under the Hinkler Regional Deal agreement, Council was required to report on the estimated total costs of the broader Hervey Bay City Centre redevelopment project.

The Australian Government subsequently reported a total investment of $136.4 million for the city centre redevelopment.

This figure includes construction of the Community Hub, associated project costs, land purchases, city centre master planning, traffic management, and public realm improvements.

The Community Hub construction contract was awarded under a Guaranteed Maximum Price arrangement.

This protects Council against construction cost overruns and allows Council to share in savings if the final cost is below the agreed contract price.

A financial audit in September 2026 confirmed an estimated final construction cost of $98.1 million, with Council's share of the savings currently estimated at approximately $7 million.

Outstanding subcontractor commitments and obligations under the 12-month defects period will need to be finalised before the project can be fully reconciled. Council currently expects this process to be completed by mid-to-late 2027.

Hinkler Regional Deal Project Leadership team meetings were held monthly throughout the project, with all Councillors receiving copies of the full agendas, which include minutes and detailed reports.

Council will provide a detailed report in the coming months in response to the motion passed at this week’s Council meeting.