Urangan Pier Rehabilitation

Urangan Pier Rehabilitation

What happened

The Urangan Pier underwent restoration works to address areas of deterioration.

Why

Regular inspections showed that parts of the pier were deteriorating and needed repairs to keep it safe and functional.

When

The works commenced late January 2025 and were completed in April 2025.

Who completed the work

Timber Restoration Services were hired to carry out the repairs.

How much did it cost

The project cost $911,183.96 (ex GST), funded by the State Government’s Works for Queensland Program.

Community impact

The pier is now safer and better for public use.

Click on the fact sheet below for more information