Whirlwind of works on Boundary Road extension

Back

Work taking place on the Boundary Road extension

Fraser Coast motorists are being urged to be mindful of changed traffic conditions around the Boundary Road extension project as a “whirlwind of works” occurs over the next few months.

Fraser Coast Regional Council Infrastructure Services Director Davendra Naidu said the final stages of construction of the new east-west road connection through Hervey Bay would require several short-term road closures.

“The Boundary Road extension will set up the rapidly growing Fraser Coast region for the future, reducing traffic congestion and taking the pressure off Boat Harbour Drive,” he said.

“We acknowledge and appreciate the patience of motorists, particularly over the past 12 to 18 months as the works expanded beyond the road reserve to existing roads. While the finish line is in sight, there will be a bit more short-term pain before we get the long-term gain.

“Part of Richard Charles Drive in Kawungan will be closed from 18 March for up to four weeks while a raised priority crossing is constructed, and the intersection of Ironbark Street and Denmans Camp Road will close for about four weeks in April/May for works in this area.

“Footpath connections near the Kawungan Way roundabout will be built during March and into April, with single-lane closures required to complete these works.

“A full closure of Denmans Camp Road will be required for about two weeks in April/May while deep lift asphalt surfacing works occur at the intersection with Boundary Road. While this closure is in place, there will be a two-way traffic arrangement in Maree Street to assist with detouring traffic.

“Asphalt works and landscaping across the Boundary Road extension project will start in March and be finished by June, with Ergon to install street lights in June and July.

“The opening of the Boundary Road extension remains on track for around July or August this year, weather and construction conditions permitting.”

The Boundary Road extension project is being funded by the Australian Government ($9.625 million) as part of the Hinkler Regional Deal initiative, the Queensland Government through the Transport Infrastructure Development Scheme ($3.272 million) and Fraser Coast Regional Council, which is also funding associated upgrades to the existing roads and drainage network.

More details about the project, including a flyover animated video, is available at https://frasercoast.engagementhub.com.au/boundary-road-extension-project