Road resurfacing works kick off in Hervey Bay
Roads in Point Vernon, Scarness and Pialba will get a fresh asphalt surface from today, making everyday trips smoother and safer for motorists, cyclists and local residents.
Fraser Coast Regional Council Roads spokesperson Cr Denis Chapman said the works target busy sections of roads that have worn over time.
“These road resurfacing works are about making everyday travel quieter, safer and easier - whether you’re doing the school run, commuting to work or heading to the shops,” he said.
The $2.3 million package will renew sections of Torquay Road, Taylor Street, Murphy Street, Anchorage Circuit, Spinnaker Drive, and North Street across Hervey Bay.
Day works will be performed where possible, and night work will be performed on the busiest stretches to keep traffic moving and limit disruption to businesses.
“Crews will start in Point Vernon on Murphy Street, North Street, Anchorage Circuit and Spinnaker Drive, before moving into Scarness and Pialba,” Cr Chapman said.
“Torquay Road (Zephyr Street to Queens Road) in Scarness will be resurfaced during the day from 29 September to 3 October.
“The busier sections in Pialba - Torquay Road (Zephyr to Hunter) and Taylor Street (Andrew to Hillyard) - are scheduled as night works from Sunday 5 October for about two-and-a-half to three weeks, Sundays to Thursdays, 6 pm to 5 am.”
Cr Chapman said the community’s patience would help ensure the work gets done safely and quickly.
“Please slow down in work zones, follow traffic controllers and allow a little extra time,” he said.
“Most sites will operate with reduced speeds and single-lane traffic. On two narrow streets, Anchorage Circuit and North Street, there will be short full closures at times.”
Residents and nearby businesses will receive letterbox notices from the contractor before work starts in their street.
Asphalt resurfacing is targeted for completion by the end of October, weather permitting. Line marking and the traffic-light sensors under the road will be reinstated after resurfacing is finished.
“These short works will bring long-term benefits - fewer pothole repairs, safer intersections and a better ride across some of our busiest local roads,” Cr Chapman said.